Longest Task, Critical Path? 🚧
A three-day task followed by another three-day task controls a six-day finish; a parallel five-day task has one day of float.
An animated teaching example with AI narration. The illustrations explain the process; they are not a recording of the app.
Video transcript
Five days is the longest task. Why does it not control this finish?
This unconstrained example uses one calendar, finish-to-start links, no lags, and no resource limits. Both paths start together and feed one finish.
A takes three days, then B takes three: six total. C takes five. The connected six-day path controls.
Give C one extra day. It uses its one day of float, tying six. The finish stays at six.
Trace the connected path, calendars, and logic to your milestone. Find the critical-path guide at os dot construction.