Construction lessons in a minute · 0:48

Same 40 Hours. Three Different Finish Dates.

Show why calendar availability changes elapsed finish dates even when working duration stays constant.

An animated teaching example with AI narration. The illustrations explain the process; they are not a recording of the app.

Published · Illustrative examples · Watch on YouTube

Video transcript

Forty hours of working duration. Three different finish dates. The missing ingredient is the calendar.

Start Thursday morning, with eight working hours each day. On a Monday-to-Friday calendar, work Thursday, Friday, Monday, Tuesday, Wednesday. Finish Wednesday afternoon.

Allow eight hours every day instead, and the same task finishes Monday. Keep weekdays only, but make Monday a holiday, and it finishes Thursday.

Every version still contains forty working hours. Check shifts, holidays, and calendar assignments before assuming the duration changed.

And verify weekend work is actually available before changing the plan. Explore the calendar guide at os dot construction.