Same 40 Hours. Three Different Finish Dates.
Show why calendar availability changes elapsed finish dates even when working duration stays constant.
An animated teaching example with AI narration. The illustrations explain the process; they are not a recording of the app.
Video transcript
Forty hours of working duration. Three different finish dates. The missing ingredient is the calendar.
Start Thursday morning, with eight working hours each day. On a Monday-to-Friday calendar, work Thursday, Friday, Monday, Tuesday, Wednesday. Finish Wednesday afternoon.
Allow eight hours every day instead, and the same task finishes Monday. Keep weekdays only, but make Monday a holiday, and it finishes Thursday.
Every version still contains forty working hours. Check shifts, holidays, and calendar assignments before assuming the duration changed.
And verify weekend work is actually available before changing the plan. Explore the calendar guide at os dot construction.
Your next step
See it on one project record.
Explore the written guide, then open the sample project to see how construction records connect.
Try it in the app- Next · Construction lessons in a minuteThe Schedule Has a Wait. Does Anyone Own It?Watch the next explainer
- ExplainerSchedule calendars: why five working days can mean different finish datesThe full written guide, with worked examples and sources.
- Video libraryMore in Construction lessons in a minuteEvery video, grouped by topic.