Your Week 12 Delivery May Need a Week 2 Submittal

Work backward from delivery through supplier lead time, review and revision allowance to find the submittal deadline.

An animated teaching example with AI narration. The illustrations explain the process; they are not a recording of the app.

Published · Illustrative examples · Watch on YouTube

Video transcript

Need equipment on site in week twelve? Your submittal might be due in week two. Here's the backward pass.

In this example, fabrication and delivery take six weeks after release. To arrive in week twelve, release must happen by week six.

Allow two weeks for initial review, plus two more for a possible revision cycle. Now your submit-by target is week two.

These are sample durations. Confirm the actual review period, supplier lead time, release conditions, and calendar before setting the dates.

Track submit-by, approval, release, and required delivery separately. An approved submittal doesn't prove the order has been released. Find the submittal-register guide at os dot construction.