The most important number on a job is not what you have spent. It is what the job will cost when it is done: the estimate at completion (EAC). EAC is cost to date plus estimated cost to complete (CTC).

The weak way to get CTC is "revised budget minus cost to date". That quietly assumes every remaining dollar will land exactly on budget, even on codes that are already overrunning. A better CTC is built from what is left: remaining quantities times realistic rates, plus open commitments, plus known exposure such as unpriced changes.

A quick cross-check is the percent-complete method: if a scope is physically 58% complete and has cost $2.61M, a straight-line projection says about $4.5M at completion. When the bottom-up CTC and the projection disagree, that gap is where the conversation should start.

CTC should be reviewed by the person who knows the work, every month, code by code. The output is the projected over or under budget on each code, and the projected gross profit on the job. That forecast feeds everything downstream: WIP, revenue recognition, cash planning and what you tell your surety.

Do it · Calculator

Estimate at completion calculator

With the defaults ($4.25M budget, $2.61M spent, 58% complete) note the EAC and projected margin. Switch to "Estimate to complete" mode and enter $1,640,000 (budget minus spent). Compare: the "budget minus spent" forecast shows no overrun at all, while the percent-complete projection does.

Open the calculator

Check yourself

Three questions, instant feedback. Get all three right to check off this lesson.

Q1Estimate at completion (EAC) equals:

Q2Why is "revised budget minus cost to date" a weak cost-to-complete?

Q3A scope is 50% physically complete and has cost $600,000. Straight-line, what is the projected cost at completion?

0 of 3 correct