A cost code is the address for a dollar of job cost. Most contractors combine a work breakdown (often based on CSI MasterFormat divisions, like 03 Concrete or 26 Electrical) with a cost type (labor, material, equipment, subcontract, other). The estimate is loaded into those codes as the original budget, and every timecard, invoice and commitment is coded against them.

The goal is comparison: budget versus actual versus forecast, code by code. That only works if the same codes mean the same thing across jobs and if people in the field can code correctly without a lookup table. Too many codes and time gets miscoded; too few and you cannot see where the job is bleeding.

Budgets change. Approved change orders add budget, and transfers between codes (from contingency, or from a code that came in under) should be recorded as budget changes, not hidden by coding cost to wherever there is room. The revised budget is original plus approved changes, and it is what cost-to-complete is measured against.

If you can answer "what did we spend on rebar on this job, and what did we think we would spend?" in under a minute, your cost code structure is doing its job.

Do it · Template

Cost-to-complete worksheet (CSV)

Open the worksheet and read the sample row (23-3300 Air duct accessories). Add three cost codes from a job you know, with original budget and any approved budget changes, and confirm the revised budget column equals original plus changes for each.

Download the template

Check yourself

Three questions, instant feedback. Get all three right to check off this lesson.

Q1A typical cost code combines:

Q2Revised budget equals:

Q3A code is overrunning, so the PM codes new cost to a code with room left. What is wrong?