Over/under billing (WIP) calculator

Are you billing ahead of the work or financing the owner's job? Cost-to-cost percent complete, earned revenue and the over/under number your bonding agent will ask about.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link

Job inputs

$
Including approved change orders.
$
Current estimate at completion, not the original bid.
$
$
Gross billings, before retainage is withheld.

ResultsLive

Gauge of billing position: under billed on the left, over billed on the rightUNDERBALANCEDOVER
% complete (cost)
0%
Earned revenue
$0
Over / (under)
$0
Projected GP
$0

Sample inputs (sample data): Riverside Medical Center, Job #24-118, plus two illustrative jobs in multi-job mode.

See what's planned

Method

How this is calculated

Contractors recognize revenue as the work gets done (percentage of completion, ASC 606 over time). Billing follows the schedule of values, so the two drift apart. The gap is over or under billing.

% complete       = cost to date ÷ estimated total cost
Earned revenue   = contract value × % complete
Over / (under)   = billed to date − earned revenue
Projected GP     = contract value − estimated total cost
GP margin        = projected GP ÷ contract value
GP to date       = earned revenue − cost to date

Reading the result

  • Over billed (billings in excess of costs and estimated earnings) is a liability. You've been paid for work you still owe. Good for cash, but it can hide a fading job.
  • Under billed (costs and estimated earnings in excess of billings) is an asset. You've done work you haven't billed. Persistent under billing often means unbilled change orders, a front-loaded cost, or an estimate that's too low.

Why the estimate matters most

Cost-to-cost is only as good as the estimated total cost. If the estimate is stale, % complete is inflated, earned revenue is overstated and under billing looks better than it is. Update cost-to-complete before you run WIP. If cost to date exceeds the estimate, this tool caps % complete at 100% and flags it.

Totals in multi-job mode are simple sums. Bonding and CPA schedules usually also show over and under billing separately (they are not netted on the balance sheet), which the footer row does.

Stop re-keying the numbers behind this math.

Project Financials tracks job costs and billing. Company Accounting is available for evaluation; certified WIP posting and close are not yet available.

Your role (optional)

Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

More free tools

RetainageRetainage held, payment due this period and balance to finish, G702 style.Change order markupPrice a CO: OH&P, tiered sub markup, insurance and bond, with a waterfall.Estimate at completionEAC, cost-to-complete, budget variance and margin fade from where the job is today.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityRule-of-thumb single-job and aggregate bonding capacity from working capital, net worth and backlog.Cash flow curveS-curve billings, retainage and pay-when-paid lag to monthly cash in, cash out and peak cash need.Punch list closeoutWeeks to clear the punch list at your real close and add rates, and the weekly close rate a target date needs.RFI response timePaste your RFI log: median and average turnaround, share answered within the contract period, and open RFIs already late.WIP report generatorDrop in a CSV of jobs, get a print-ready WIP report: over/under billing, margin, backlog, loss jobs. Runs in your browser.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file