Owners review change order pricing line by line, so price it the way they read it. Start with direct cost by type: labor (at burdened rates), material, equipment and subcontract. Then add markups in the order your contract allows.

Self-performed work usually carries overhead and profit (OH&P) at the contract rate. Subcontract work usually carries a lower GC markup, because the sub's quote already includes its own overhead and profit; some contracts tier it so larger sub amounts get a smaller percentage. Insurance and bond costs are often added last, as a percentage of the subtotal.

Two things keep a change order from stalling. Back-up: quotes, quantities, time and material tickets, and a clear tie to the event that caused the change. And consistency: the same markup rules, applied the same way, on every change. A reviewer who finds one inconsistency will re-check all of them.

Sample data: CO #14 on Riverside is $78,100 of cost (mostly a $68,000 sub quote from Summit Mechanical) plus $8,300 of markup, for $86,400.

Do it · Calculator

Change order markup calculator

The calculator opens on CO #14 ($86,400). Change the subcontract amount to $150,000 and look at the waterfall: note how much of the sub markup is at the tier 1 rate and how much at tier 2. Then set both tier rates equal and compare the total.

Open the calculator

Check yourself

Three questions, instant feedback. Get all three right to check off this lesson.

Q1Why is GC markup on subcontract work often lower than OH&P on self-performed work?

Q2Insurance and bond on a change order are commonly calculated:

Q3What most often stalls an owner's change order review?

0 of 3 correct