Esc

↑↓ move↵ openIndex · Pagefind
Analytics

Estimate at completion

Definition

The forecast total cost of a job when finished: cost to date plus estimated cost to complete.

Estimate at completion (EAC) is what you now expect the job to cost in total. The formula is cost to date plus cost-to-complete. Compared with the revised budget, it shows the projected overrun or underrun; compared with contract value, it shows projected gross profit.

Why it matters

EAC is the number that ties operations to the financial statements. It sets percent complete under the cost-to-cost method, which sets earned revenue. When EAC moves, reported profit moves. Tracking EAC month over month is also the cleanest way to spot margin fade early.

Worked example

Illustrative: Riverside Medical Center.

  • Cost to date: $31.7M
  • Cost to complete: $11.98M
  • EAC: $43.68M
  • Contract (incl. $1.1M approved COs): $49.3M
  • Projected gross profit: $5.62M, or 11.4%

If CO #14 is approved at $86,400 and its cost estimate is, say, $75,000, contract rises to $49,386,400 and EAC rises to $43,755,000. The CO adds $11,400 of margin. Both sides have to move together, or the forecast is wrong.

Common mistakes

  • Adding a change order to contract value without adding its cost to EAC, which inflates margin.
  • Building EAC from accounting actuals alone, without the PM’s view of remaining work.
  • Revising EAC only at quarter-end.

How os.construction handles it

We’re building EAC to update as costs, commitments and approved changes post, with a monthly PM sign-off so the forecast always has an owner.