Month-end WIP prep checklist

The steps to a defensible work-in-progress schedule, job by job, every month.

os.construction
Free template
Company
Period ending
Prepared by
Reviewed by

1 · Cut off costs

DoneItemOwnerDate
AP invoices for the period entered and coded to job and cost code
Payroll through period end posted, including burden
Unbilled costs accrued (work performed, invoice not yet received)Ask each PM for received-not-invoiced items.
Equipment and internal charges posted to jobs
Committed costs current: subcontract and PO change orders entered

2 · Update the forecast

DoneItemOwnerDate
PM updates cost-to-complete for every cost codeBottom-up: remaining work, not budget minus cost to date.
Estimated total cost (EAC) = cost to date + cost to complete
Contract value updated for approved change ordersUnapproved COs: follow your revenue policy and your CPA; do not count them by default.
Projected gross profit and margin recalculated
Loss jobs flagged: full anticipated loss recognized now

3 · Compute WIP

% complete (cost-to-cost) = cost to date ÷ estimated total cost
Earned revenue = % complete × current contract value
Over / (under) billing = billed to date − earned revenue
Positive = over billed (liability) · Negative = under billed (asset)
DoneItemOwnerDate
Billed to date tied to AR / pay apps for every job
Over / under billing calculated per job
Fade check: margin vs last month and vs original estimateExplain every move over your threshold.
Retainage receivable and payable reconciled

4 · Review and post

DoneItemOwnerDate
WIP review meeting held with PMs, ops lead and CFO
Changes from the review captured in the forecast
Over / under billing journal entry posted
WIP schedule tied to the general ledger (revenue, cost, over/under)
Backlog updated: contract value remaining to be earned
WIP package saved for lender, surety and bonding agent as required

Illustrative example: contract $10,000,000; cost to date $4,200,000; estimated total cost $8,750,000 → 48.0% complete → earned revenue $4,800,000. Billed to date $5,100,000 → over billed $300,000.

Template from os.construction/resources/templates. Free to use and adapt.Requirements vary by contract and state. Your contract documents govern.