Project closeout checklist
From substantial completion to final payment and retainage release. Work it top to bottom.
os.construction
Free template
Free template
Project
Job #
Owner
Architect
Substantial completion date
Final completion target
1 · Substantial completion
| Done | Item | Owner | Date |
|---|---|---|---|
| Contractor punch list walk completedYour own list first, before the architect walks. | |||
| Architect / owner punch list received and distributed to subsEach item assigned to a responsible trade with a due date. | |||
| Certificate of Substantial Completion executedOften AIA G704. Fixes the date warranties start and LD exposure stops. | |||
| Temporary or final certificate of occupancy obtained | |||
| Utilities, insurance and security responsibilities transferred to ownerConfirm the transfer date in writing. |
2 · Inspections and systems
| Done | Item | Owner | Date |
|---|---|---|---|
| Final building, fire and life-safety inspections passed | |||
| MEP systems tested, balanced and commissionedTAB report and commissioning sign-off on file. | |||
| Owner training sessions held and attendance logged | |||
| Keys, access cards and combinations turned over with a signed receipt |
3 · Closeout documents
| Done | Item | Owner | Date |
|---|---|---|---|
| As-built / record drawings submittedEvery field change and RFI answer reflected. | |||
| Operation and maintenance manuals submitted | |||
| Warranties and guarantees collected from every tradeStart dates tied to substantial completion unless the contract says otherwise. | |||
| Attic stock / spare materials delivered and receipted | |||
| Final punch list items closed and verified |
4 · Change orders and cost
| Done | Item | Owner | Date |
|---|---|---|---|
| All pending change orders resolved, approved or withdrawnNothing should still be "pending" at final. | |||
| Subcontract and PO change orders match owner COs | |||
| Back-charges documented and settled with subs | |||
| Final job cost reviewed: all invoices in, accruals clearedCompare final cost to the last WIP forecast to measure fade. |
5 · Final payment and retainage
| Done | Item | Owner | Date |
|---|---|---|---|
| Final subcontractor pay apps received | |||
| Conditional final lien waivers collected from every sub and supplierIncludes lower tiers where your contract or state law requires. | |||
| Consent of surety to final payment obtained (bonded jobs)Often AIA G707. | |||
| Final owner pay app with retainage release submitted | |||
| Unconditional final lien waivers exchanged once funds clear | |||
| Retainage paid out to subs per subcontract terms |
6 · Wrap-up
| Done | Item | Owner | Date |
|---|---|---|---|
| Project files archived: contract, COs, RFIs, submittals, daily logs, photos | |||
| Lessons-learned review with PM, super and estimating | |||
| Warranty-period reminders set (e.g. 11-month walk) |
Tip: retainage is the money most often left on the table at closeout. Track lien waivers and closeout documents from day one, not in the last month.
Template from os.construction/resources/templates. Free to use and adapt.Requirements vary by contract and state. Your contract documents govern.