Change order request

Price a change, document why it happened, and get it signed before the work is billed.

os.construction
Free template
Project
Job #
CO request #
Date submitted
To (owner / architect)
From (contractor)
Related RFI / ASI / change event
Response needed by

1 · Description of change

Scope added, deleted or changed. Reference drawings and spec sections.

2 · Reason for change

Owner requestDesign change / ASIHidden or unforeseen conditionRFI responseCode / AHJ requirementAllowance reconciliationOther

Supporting documents attached

RFI and responseRevised drawings / sketchSub and supplier quotesT&M ticketsPhotosSchedule fragnet

3 · Cost breakdown

Cost elementBasis / notesAmount
Labor (self-performed, incl. burden)
Material
Equipment
Subcontract (attach quote)
Subtotal: cost of the work
Overhead and profit ( ____ % per contract)
Subcontractor markup ( ____ % per contract)
Insurance and bond ( ____ %)
Total requested change to contract sum

Illustrative example (Riverside Medical Center sample job, CO #14, fire dampers from RFI-212): subcontract $68,000 (Summit Mechanical CCO-03) + supervision labor $6,500 + firestopping material $3,600 = cost $78,100. Fee and sub markup $6,014 + insurance and bond $2,286 = markup $8,300. Total requested $86,400.

4 · Schedule impact

No change to contract timeExtension requested
Calendar days requested
Revised completion date
Activities affected
Float consumed (days)

5 · Approval

Approved as submittedApproved as notedRevise and resubmitRejected

Notes / conditions

ContractorSignatureName, title, date
Architect / engineerSignatureName, title, date
OwnerSignatureName, title, date

Not a replacement for AIA G701 or your contract's change order form. Use it to price and document the request; follow the notice periods and markup limits in your contract. Do not bill the work until the change order is executed.

Template from os.construction/resources/templates. Free to use and adapt.Requirements vary by contract and state. Your contract documents govern.