# Change order log template

Excel workbook with live formulas: https://os.construction/templates/change-order-log-template.xlsx

**Project:** ______________________  
**Original contract:** ______________________  
**As of:** ______________________  
**Kept by:** ______________________  

## Change order log (sample rows)

| CO # | Title | Origin | Status | Requested amount | Approved amount | Days in review | Billed on pay app # | Revised contract (running) |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| CO-001 | Rock removal at footing F-7 | Hidden condition | Approved | $24,800 | $21,500 | 15 | 2 | $20,171,500 |
| CO-002 | Add card readers at suite 300 | Owner request | Approved | $6,850 | $6,850 | 7 | 3 | $20,178,350 |
| CO-003 | Concrete mix change for cold weather | Value engineering | Rejected | $9,400 |   | 18 |   | $20,178,350 |
| CO-004 | Revised footing detail at grid C | Design change / ASI | Approved | $18,200 | $16,500 | 19 | 4 | $20,194,850 |
|   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |

## How to use it

1. Enter the original contract and an as-of date at the top. Days in review count to the owner’s decision, or to the as-of date while a change is still open.
2. Add a row as soon as a change is likely to become a change order, with its origin and the RFI, ASI or change event it came from.
3. Move the status along as it happens: Draft, Pricing, Submitted, then Approved, Rejected or Void. Record the date you submitted it and the date the owner decided.
4. When it is approved, enter the approved amount and days, issue the matching subcontract change orders and record the pay app it goes on.
5. Review the Flag column and the Summary sheet in the weekly meeting: approved but not billed, sub COs not issued, and changes stuck in review for more than three weeks.

Template by os.construction: https://os.construction/resources/templates/change-order-log. Sample rows are illustrative; your contract and specifications govern.