# Buyout log template

Excel workbook with live formulas: https://os.construction/templates/buyout-log-template.xlsx

**Project:** ______________________  
**Job #:** ______________________  
**As of:** ______________________  
**Kept by:** ______________________  

## Buyout log (sample rows)

| Cost code | Scope / bid package | Buyout budget | Status | Award amount | Scope gaps carried | Leveled buyout cost | Savings / (loss) | Days to need-by | Flag |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| 03-3000 | Cast-in-place concrete | $2,240,000 | Executed | $2,105,000 | $18,000 | $2,123,000 | $117,000 |   |   |
| 05-1200 | Structural steel and deck | $1,960,000 | Executed | $1,885,000 | $0 | $1,885,000 | $75,000 |   |   |
| 07-5400 | Roofing | $610,000 | Executed | $598,000 | $0 | $598,000 | $12,000 |   |   |
| 08-4100 | Storefront and glazing | $430,000 | Awarded | $412,000 | $9,500 | $421,500 | $8,500 |   |   |
| 09-2900 | Gypsum board and framing | $2,960,000 | Executed | $3,120,000 | $0 | $3,120,000 | ($160,000) |   | Bought out over budget |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |

## How to use it

1. List every bid package with its cost code and buyout budget before bidding starts, and set the need-by award date from the procurement schedule (long-lead items first).
2. Move the status along as packages go out, come in and get leveled. Leveling means adding back the cost of anything a bidder excluded that you still have to buy.
3. When you award, enter the award and the scope gaps you carry. The log computes the leveled cost and the saving or overrun against the budget.
4. Review the flags weekly: packages bought out over budget, awards past their need-by date and awards due within 14 days.
5. Use the Summary in the monthly cost review: share of the budget bought out, net savings and, on GMP or cost-plus work, the split your contract sets between owner and contractor.

Template by os.construction: https://os.construction/resources/templates/buyout-log. Sample rows are illustrative; your contract and specifications govern.