# ASI log template

Excel workbook with live formulas: https://os.construction/templates/asi-log-template.xlsx

**Project:** ______________________  
**Architect:** ______________________  
**Contractor:** ______________________  
**Review period (days):** ______________________  
**As of:** ______________________  

## ASI log (sample rows)

| ASI # | Date issued | Title / instruction | Sheets and spec sections | Received by GC | Review due | Cost or time impact? | Change document | Status | Flag |
| --- | --- | --- | --- | --- | --- | --- | --- | --- | --- |
| ASI-001 | 6/4/2026 | Revise door hardware set 7 at stair doors | A-601; 08 71 00 | 6/5/2026 | 6/12/2026 | No | None | Incorporated |   |
| ASI-002 | 6/18/2026 | Relocate floor box in conference 214 | E-201 | 6/18/2026 | 6/25/2026 | Yes: cost | PCO | Distributed |   |
| ASI-003 | 7/9/2026 | Add blocking for owner-furnished monitors, L2 | A-501; 06 10 00 | 7/10/2026 | 7/17/2026 | Yes: cost | None | Distributed | Impact claimed, no change document |
| ASI-004 | 8/13/2026 | Clarify sealant color at storefront | 07 92 00 | 8/13/2026 | 8/20/2026 | No | None | Incorporated |   |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |
|   |   |   |   |   |   |   |   |   |   |

## ASI form: the fields to capture

| Field | Entry |
| --- | --- |
| ASI number and date issued |   |
| Project and contract |   |
| Issued to (contractor) and issued by (architect) |   |
| Instruction: what changes, in plain words |   |
| Drawings, sheets and specification sections affected |   |
| Attachments (sketches, revised sheets) |   |
| Origin (RFI answer, coordination, owner request, code) |   |
| Statement: issued without change in contract sum or time |   |
| Contractor response: no impact / cost or time impact claimed, with notice date |   |
| Architect signature and date |   |
| Owner signature and date, if the contract requires it |   |
| Contractor received by and date |   |

## How to use it

1. Set the review period: the days you allow to price an ASI, or the notice period your contract gives for claiming that an instruction changes cost or time, whichever is shorter.
2. Log each ASI the day it arrives, with the sheets and spec sections it touches and the RFI it answers, if any.
3. Send it to every affected sub the same day and ask one question: does this change your cost or time? Record the answer as the impact.
4. If there is an impact, give notice under your contract before the review date and record the change document: a PCO for pricing, a construction change directive if the owner directs the work before price is agreed, or a change order.
5. Post the ASI to the current set and mark it incorporated. Work the flags weekly so no priced ASI is left without paper.

Template by os.construction: https://os.construction/resources/templates/asi-log. Sample rows are illustrative; your contract and specifications govern.